Project stage Design (2009 - 2012)

From
28 July 2009
To
30 August 2012

Summary

The Design phase includes Schematic Design (SD), Design Development (DD) and Contract Documentation (CD).

Details

During the Schematic Design (SD) phase, the architects communicate their proposed design to the client. At this stage, not all details will be worked out but the overall design approach will be made clear.

For the Design Development (DD), the architects will continue to develop the design and will develop typical details during this time.

The Contract Documentation (CD) will have been produced by the architects to be submitted for building permit applications, and can also be used to solicit construction proposal from contractors.

Related Entries

Timeline

 2011 - 2012 Old building and pre-existing conditions
       2009 Design competition
             2009 - 2012 Design
                   2012 - 2013 Pre-construction
                         2013 - 2014 Construction
                               2014 Post-construction

Related Design competition events