Construction phase event Cantilever structure (2014)

From
May 2014
To
May 2014
Functions
Main construction element

Summary

The cantilever construction phase included:

  • Temprorary supports to Level 2 (including footing)
  • Steel, Deck and Bracing, Levels 2-5
  • Final connections and remove temporary supports
  • Reo and pour levels 2 - 5

Details

Events

1 May 2014 - 27 May 2014
Scheduled timeframe

Related Entries

Timeline

 2013 - Site establishment
       2013 - Excavation, retention and foundation works
             2013 - 2014 Main concrete structure
                   2014 Cantilever structure
                         2014 Roof works
                               2013 - 2014 Atrium works and specialised structures
                                     2014 Lift and plant works
                                           2014 Facade works
                                                 2014 - Services and finishes
                                                       2014 External works