Construction phase event Cantilever structure (2014)
- From
- May 2014
- To
- May 2014
- Functions
- Main construction element
Summary
The cantilever construction phase included:
- Temprorary supports to Level 2 (including footing)
- Steel, Deck and Bracing, Levels 2-5
- Final connections and remove temporary supports
- Reo and pour levels 2 - 5
Skip to
Details
Events
- 1 May 2014 - 27 May 2014
- Scheduled timeframe
Related Entries
Timeline
2013 - Site establishment
2013 - Excavation, retention and foundation works
2013 - 2014 Main concrete structure
2014 Cantilever structure
2014 Roof works
2013 - 2014 Atrium works and specialised structures
2014 Lift and plant works
2014 Facade works
2014 - Services and finishes
2014 External works