Construction phase event Retention and excavation (2013)

From
2013
To
2013
Functions
Secondary construction element

Summary

The retention and excavation works are a secondary construction element required to complete Excavation, retention and foundation works.

It consists of four parts:

  • North
  • South
  • East
  • West

North, South and East Retention & Excavation works comprise:

  1. Construct capping beam
  2. Excavate to 1st anchor level
  3. Install 1st row anchors
  4. Spray walls
  5. Excavate to 2nd anchor level
  6. Install 2nd row anchors
  7. Spray walls
  8. Final excavate & spray

West Retention & Excavation Works comprise:

  1. Construct capping beam
  2. Excavate to 1st anchor level
  3. Install 1st row anchors
  4. Spray walls
  5. Excavate & spray
  6. Final excavate & spray

Details

Events

25 May 2013 - 29 August 2013
Scheduled timeframe

Related Entries

Timeline

 2013 Piling
       2013 Retention and excavation
             2013 Foundation basement slab works