Construction phase event Foundation basement slab works (2013)
- From
- August 2013
- To
- October 2013
- Functions
- Secondary construction element
Summary
The Foundation basement slab works are a secondary construction element required to complete the exacavation, retention and foundation works. They include:
- Area 1 Slab (Lower)
- Area 2 Slab (Lower)
Area 1 and 2 Slabs comprise of:
- Pad & Strip Footing
- Sub-Floor Services
- Construct Slab on Ground
- Erect & Prop Precast
- Area 3 Slab (Upper)
- Area 4 Slab (Upper)
Area 3 and 4 Slabs comprise of:
- Pad & Strip Footing
- Backfill against Pour 1 Walls
- Sub-Floor Services
- Construct Slab on Ground
- Area 5 Slab (Upper)
- Area 6 Slab (Upper)
Area 5 and 6 Slabs comprise of:
- Backfill against Pour 2 Walls
- Pad & Strip Footing
- Sub-Floor Services
- Construct Slab on Ground
Skip to
Details
Events
- 10 August 2013 - 22 October 2013
- Scheduled timeframe
Related Entries
Timeline
2013 Piling
2013 Retention and excavation
2013 Foundation basement slab works