Construction phase event Foundation basement slab works (2013)

From
August 2013
To
October 2013
Functions
Secondary construction element

Summary

The Foundation basement slab works are a secondary construction element required to complete the exacavation, retention and foundation works. They include:

  • Area 1 Slab (Lower)
  • Area 2 Slab (Lower)

Area 1 and 2 Slabs comprise of:

  1. Pad & Strip Footing
  2. Sub-Floor Services
  3. Construct Slab on Ground
  4. Erect & Prop Precast
  • Area 3 Slab (Upper)
  • Area 4 Slab (Upper)

Area 3 and 4 Slabs comprise of:

  1. Pad & Strip Footing
  2. Backfill against Pour 1 Walls
  3. Sub-Floor Services
  4. Construct Slab on Ground
  • Area 5 Slab (Upper)
  • Area 6 Slab (Upper)

Area 5 and 6 Slabs comprise of:

  1. Backfill against Pour 2 Walls
  2. Pad & Strip Footing
  3. Sub-Floor Services
  4. Construct Slab on Ground

Details

Events

10 August 2013 - 22 October 2013
Scheduled timeframe

Related Entries

Timeline

 2013 Piling
       2013 Retention and excavation
             2013 Foundation basement slab works

is part of